Termination of Off-Plan Real Estate Sale Agreements in Dubai

Introduction

 

In the present economic climate, terminating off-plan real estate sale agreements in Dubai is a prominent issue. The procedure and remedies differ significantly depending on whether termination is sought by a developer following a purchaser’s default, or by a purchaser following a developer’s default, including delay in completion.

 

Governing Legislation:

 

➢ Dubai Law No. 13 of 2008 (amended by Law No. 19 of 2017 and Law No. 19 of 2020).

 

➢ Federal Decree-Law No. 25 of 2025 (Civil Transactions Law, effective 1 June 2026).

 

➢ Federal Law No. 5 of 1985 (Civil Code, applies to transactions prior to 1 June 2026).

 

1. Termination by Developer for Purchaser Non-Payment

 

Statutory Basis & Mandatory Procedure

 

A developer cannot immediately terminate a sale and purchase agreement (SPA) upon purchaser default, which is usually non-payment of a due instalment. A developer must strictly follow the procedures mandated by Article 11(a) of Law No. 13 of 2008, as amended:

 

a) DLD Notification: Notify the Dubai Land Department (DLD) of the default.

 

b) Statutory 30-Day Notice: DLD serves a 30-day notice to the purchaser to remedy the breach or reach an amicable settlement.

 

c) Compliance Document: If the 30-day notice period expires without the breach being remedied, DLD issues an official document confirming procedural compliance and project completion percentage.

 

d) Unilateral Action: The developer may then terminate the SPA of its own accord without needing a court ruling or arbitration award.

 

Amounts Retainable by Developer Upon Termination

 

The project completion percentage determines the developer’s financial remedies under Article 11(a)(4):

 

Project Completion Status

Allowable Developer Financial Remedies & Options

More than 80% Complete

Option A: Maintain the SPA, retain all paid amounts, and claim the remaining balance.


Option B: Request the DLD to sell the unit via public auction to collect outstanding amounts.


Option C: Terminate the SPA, retain up to 40% of the purchase price, and refund the excess within one year (or 60 days of resale).

Between 60% and 80% Complete

Terminate the SPA, retain up to 40% of the purchase price, and refund the excess within one year (or 60 days of resale).

Less than 60% Complete

Terminate the SPA, retain up to 25% of the purchase price, and refund the excess within one year (or 60 days of resale).

Construction Not Commenced (Beyond developer control)

Where non-commencement is not due to the developer’s negligence or omission, terminate the SPA and return all purchase monies to the purchaser.

 

2. Termination by Purchaser for Developer Default

 

Default – Developer Delay in Completion

 

A purchaser’s rights where the developer delays completion of the unit arise under the SPA, general contractual principles, and the applicable Civil Transactions Law. For SPAs governed by Federal Decree-Law No. 25 of 2025, Article 234 permits a purchaser, following notice, to seek performance or rescission where the developer fails to perform its obligation when due, together with damages where appropriate. For transactions governed by Federal Law No. 5 of 1985, the corresponding principles are set out in Article 272 of the former Civil Code. The applicable law should be determined having regard to the transitional provisions of the 2025 Civil Transactions Law, which came into force on 1 June 2026.

 

Materiality & Legally Excused Delays

 

Not all delays entitle a purchaser to terminate. Whether a delay justifies rescission will depend on the terms of the SPA and the circumstances of the case, including the extent and materiality of the delay, any contractual completion date, extension or grace period, any legally recognized justification for the delay, and whether the breach is sufficiently significant to warrant rescission.

 

In particular, a purchaser’s right to rescind for delay may be displaced or qualified in the following circumstances:

 

➢ Force Majeure: Under Article 236(1) of the 2025 Civil Transactions Law, true force majeure terminates the contract by operation of law. Mere increased cost, inconvenience or difficulty in performance will not generally amount to force majeure. Whether a particular event constitutes force majeure will depend on the circumstances, including whether the event was beyond the affected party’s control and whether it actually rendered the relevant contractual obligation impossible. However, it requires absolute impossibility of performance (e.g., severe regulatory blocks, infrastructure failures), not just increased costs or difficulties. The burden of proving the force majeure event, and the absence of any fault on its part, lies with the developer.

 

➢ Grace Periods: Contractual extensions and grace periods in SPAs will generally be relevant and enforceable according to their terms. However, where an SPA constitutes a contract of adhesion (i.e. standardised, pre-written agreement), a court may modify an unfair term, or relieve the adhering party from it, where justice so requires, including potentially an unfair extension provision. This power arises under Article 248 of the 1985 Civil Code and Article 223 of the 2025 Civil Transactions Law, as applicable. Similarly, where an SPA provides for agreed compensation for delay, the amount may be subject to judicial review. Under Article 390 of the 1985 Civil Code, the court may, at the request of either party, adjust the agreed compensation so that it corresponds to the actual loss suffered. Under Article 340 of the 2025 Civil Transactions Law, the court’s power to adjust agreed compensation is subject to the specific grounds set out in that provision, including whether the amount is excessive, the principal obligation has been partly performed, or the creditor has contributed to the loss.

 

➢ Project Cancellation: The Real Estate Regulatory Agency (RERA) may cancel a project via a reasoned decision, under Dubai Law No. 8 of 2007 concerning Escrow Accounts for Real Estate Development. In that case, the purchaser’s position will generally be governed by the refund and liquidation framework applicable to cancelled projects, including the developer’s obligation to refund amounts paid, rather than by a contractual claim for rescission.

 

Other Permitted Grounds for Purchaser Termination

 

Under Article 20 of the Implementing Regulation of Law No. 13 of 2008, issued by Executive Council Resolution No. 6 of 2010, purchasers can apply to courts to terminate if the developer:

 

➢ Refuses to deliver the final SPA without a DLD-accepted reason.

 

➢ Declines to settle payments according to RERA construction milestones.

 

➢ Makes material changes to agreed unit specifications.

 

➢ Delivers a unit unfit for use due to material construction defects.

 

➢ Commits any other breach that justifies termination under the law.

 

Conclusion

 

Overall, Dubai law strikes a careful balance between the rights of developers and purchasers.

 

A developer may terminate an SPA for purchaser default without a court order, but only after completing the DLD notification and 30-day notice procedure under Article 11 of Law No. 13 of 2008. The amount it may then retain depends on the stage of completion: up to 25% of the purchase price where the project is less than 60% complete, and up to 40% where it is 60% complete or more, with the further options of enforcing the SPA or seeking a public auction once completion exceeds 80%. Where construction has not commenced for reasons beyond the developer’s control, all amounts paid must be refunded.

 

A purchaser seeking to terminate for developer delay or other non-performance must rely on the SPA, Article 234 of the 2025 Civil Transactions Law or Article 272 of the former Civil Code (as applicable), and the grounds set out in Article 20 of Executive Council Resolution No. 6 of 2010. The delay must be material, unjustified and outside any contractual grace period. Force majeure will excuse a delay only where performance has become genuinely impossible through no fault of the developer; increased cost or difficulty is not enough. Where RERA cancels a project, the developer must refund all purchaser payments under Dubai Law No. 8 of 2007.

 

***

 

Afridi & Angell advises and represents purchasers, investors, sellers, developers, brokers and others with respect to real estate and construction-related termination matters. Please feel free to contact us. ■

Commercial Real Estate Financing: Overview (UAE)

This Practice Note discusses the process of financing commercial real estate in the UAE. It provides guidance for borrowers and lenders on common forms of commercial real estate ownership and financing, the priority and perfection of security interests in real property, and the fundamental steps involved in financing commercial real estate, including loan due diligence, key transaction documents and loan terms, and closing mechanics. This Note also discusses lender remedies in the event of a borrower default.

The Rise of Data Centres: Commercial Real Estate and Legal Considerations in the UAE and Dubai

The rapid growth of artificial intelligence (AI), cloud computing, and digital services has significantly increased demand for data centres worldwide. In the UAE, particularly Dubai, this trend is not only transforming the technology sector but also reshaping commercial real estate, positioning data centres as critical infrastructure assets rather than niche developments.

 

This article provides a concise overview of how data centres are influencing real estate in the UAE, with a focus on structuring, leasing, and key legal considerations.

 

AI and Digital Demand Driving Real Estate

 

The UAE has actively positioned itself as a leader in AI and digital transformation, supported by initiatives from the UAE Artificial Intelligence Office and the Dubai Digital Authority. These initiatives are driving demand for:

 

➢  Cloud and hyperscale infrastructure;

 

➢ AI processing and data storage capacity; and

 

➢  Secure, low-latency digital environments.

 

As a result, data centres are now viewed as core infrastructure, directly influencing land use, development strategies, and investment decisions across the real estate sector.

 

Dubai as a Regional Data Centre Hub

 

Dubai has emerged as a leading location for data centre development due to its:

 

➢ Strategic position between Europe, Asia, and Africa;

 

➢ Advanced telecommunications and logistics networks; and

 

➢ Business-friendly regulatory environment.

 

Key areas supporting this growth include Dubai Internet City, Dubai Silicon Oasis, and Dubai Industrial City, where infrastructure and regulatory frameworks support large-scale developments.

 

Global providers such as Amazon Web Services and Microsoft Azure have also established a presence in the UAE, further reinforcing demand.

 

A New Type of Real Estate Asset

 

Data centres differ from traditional commercial assets in several key respects:

 

a. Infrastructure and Power-Driven Value: access to reliable and scalable electricity, often coordinated with Dubai Electricity and Water Authority, is a primary factor in site selection and valuation.

 

b. Long-Term Leasing Models: leases are typically long-term (10–20 years) and structured around power capacity rather than floor area, often backed by strong institutional tenants.

 

c. Free Zone Integration: many data centres are located in free zones regulated by entities such as the Dubai Development Authority, offering benefits including 100% foreign ownership and streamlined licensing.

 

Legal and Regulatory Framework

 

Although there is no single law governing data centres in the UAE, several legal frameworks are relevant.

 

a. Planning and Land Use: developments must comply with zoning and regulatory approvals, including those from free zone authorities and master developers. Key considerations include:

 

➢ Permitted use classifications;

 

➢ Environmental and operational compliance (e.g. cooling, noise); and

 

➢ Power and infrastructure approvals.

 

b. Applicable UAE Laws: core legal principles derive from:

 

➢ UAE Civil Code (Federal Law No. 5 of 1985), governing contractual relationships; and

 

➢ Dubai Law No. 26 of 2007 (as amended), which regulates landlord–tenant relationships, although data centre agreements often extend beyond standard lease structures.

 

c. Ownership and Structuring: data centres are typically held through:

 

➢ Special purpose vehicles (SPVs);

 

➢ Joint venture arrangements; or

 

➢ Build-to-suit structures for anchor tenants.

 

Structuring must account for licensing, ownership restrictions, and operational requirements, particularly where free zones are involved.

 

d. Financing: given their infrastructure nature, financing arrangements are more complex than traditional real estate and often include:

 

➢ Mortgages over land and assets;

 

➢ Assignment of lease income; and

 

➢ Direct agreements with key tenants, including step-in rights for lenders.

 

Leasing: Key Differences

 

Data centre leases in Dubai differ significantly from standard commercial leases.

 

a. Power-Based Commercial Terms: leases are commonly structured around contracted power usage (kW/MW), with minimum commitments and “take-or-pay” provisions.

 

b. Service Levels: agreements include detailed service level provisions covering uptime, redundancy, and remedies for outages—reflecting the critical nature of operations.

 

c. Fit-Out and Infrastructure: tenants often install substantial technical equipment. Legal documents must address:

 

➢ Ownership of equipment;

 

➢ Integration with base infrastructure; and

 

➢ End-of-term obligations.

 

Market Impact

 

The rise of data centres is reshaping the UAE real estate landscape:

 

➢ Developers are prioritising infrastructure and power access;

 

➢ Landlords are adapting to more complex, long-term leasing structures; and

 

➢ Investors are increasingly attracted to the stable, long-term income these assets provide.

 

Government initiatives, including those led by the UAE Ministry of Artificial Intelligence, continue to reinforce the strategic importance of digital infrastructure.

 

Conclusion

 

Data centres represent a significant shift in UAE commercial real estate from traditional space-driven assets to infrastructure-led investments. While existing laws such as the UAE Civil Code (Federal Law No. 5 of 1985) and Dubai Law No. 26 of 2007 provide the legal foundation, their application in this context requires more tailored and sophisticated structuring.

 

As demand continues to grow, success in this sector will depend on aligning real estate strategies with technical requirements, regulatory frameworks, and the UAE’s broader digital economy vision. ■

Fractional Ownership in Dubai: Legal Structuring and Strategic Advantages in a Softening Market

Fractional ownership, in simple terms, allows multiple investors to jointly own a single property, each holding a defined share. Rather than purchasing an entire asset, an investor acquires a “fraction”, typically entitling them to a proportional share of rental income and any future sale proceeds.

 

In Dubai, this is not a standalone legal regime but a structuring approach built on existing property and corporate laws. Its appeal has grown in recent years as property values have matured and, more recently, as the market shows signs of stabilisation. In this context, fractional ownership provides a more measured and flexible route into real estate investment.

 

Legal Framework and Structuring Considerations

 

Fractional ownership operates within Dubai’s established legal framework. Property ownership and registration are administered by the Dubai Land Department, with regulatory oversight from the Real Estate Regulatory Agency. There is no specific “fractional ownership law”; instead, the model relies on a combination of property rights, contractual arrangements, and, in many cases, corporate structuring.

 

Two principal structures are commonly adopted:

 

a.)  Co-Ownership (Tenancy in Common)

 

Under this model, multiple investors are registered directly on the title, each holding an undivided share in the property. While legally straightforward, this structure relies heavily on contractual agreements between co-owners to regulate matters such as leasing, use, cost sharing, and disposal. Without clear documentation, co-ownership can lead to practical difficulties, particularly where investor interests diverge.

 

b.)  SPV-Based Ownership

 

More commonly, the property is held through a special purpose vehicle (SPV), with investors holding shares in that entity rather than the property directly. This structure is generally preferred in practice as it centralises ownership and simplifies administration. It also allows for clearer governance through shareholder agreements, easier transfer of interests, and more efficient management of the asset. SPVs are often established in financial free zones, which can provide additional legal certainty and familiarity for international investors.

 

In both cases, the legal robustness of the structure depends less on the form itself and more on the quality of the underlying contractual framework.

 

Advantages in a Softening Market Context

 

In a slightly downturned or stabilising market, fractional ownership becomes particularly relevant as a more defensive and flexible investment approach.

 

a.)  Capital Efficiency and Risk Mitigation

 

One of the most immediate advantages is the reduced capital outlay. Investors can access real estate with a smaller initial commitment, which naturally limits exposure to short-term market fluctuations. This is especially relevant in a softer market, where pricing may be uncertain and investors may prefer to avoid deploying large amounts of capital at a single point in time.

 

b.)  Access to Prime and Income-Producing Assets

 

Fractional ownership is frequently applied to completed, income-generating properties in established locations. These assets tend to be more resilient in weaker market conditions, benefiting from stronger tenant demand and more stable occupancy levels. From a legal perspective, such properties are typically fully registered, which enhances certainty of title and enforceability.

 

c.)  Income Yield as a Defensive Mechanism

 

Investors receive a share of rental income in proportion to their ownership interest. In periods where capital appreciation slows or temporarily reverses, this income stream can provide a degree of stability and help offset holding costs. The presence of professional management arrangements in many fractional structures further supports consistent income generation.

 

d.)  Cost Allocation and Operational Efficiency

 

Ongoing costs, such as service charges, maintenance, and management fees are shared among investors. This reduces the financial burden on any single party and can make holding the asset more sustainable during periods of market softness, when margins may be tighter.

 

e.)  Enhanced Exit Optionality

 

Although fractional interests are not as liquid as publicly traded assets, they often offer more flexibility than traditional whole-property ownership. Well-structured arrangements typically include transfer provisions, pre-emption rights, or platform-based resale options. In a slower market, where disposing of an entire asset may take time, this can provide a meaningful advantage.

 

f.)  Governance and Decision-Making

 

Particularly in SPV-based structures, governance can be clearly defined through shareholder agreements. Voting thresholds, reserved matters, and management roles can be set out in advance, reducing the risk of disputes and ensuring that the asset can be managed effectively even where multiple investors are involved. This becomes increasingly important in a down cycle, where timely and coordinated decision-making is critical.

 

Key Legal Risks and Considerations

 

Despite its advantages, fractional ownership requires careful legal structuring to function effectively. The following areas are of particular importance:

 

➢ Title and registration: Ensuring that ownership is properly recorded, whether directly or through an SPV, and aligned with DLD requirements

 

➢ Governance arrangements: Clearly defining decision-making processes to avoid deadlock or disputes among investors

 

➢ Exit mechanisms: Providing workable routes for transfer or sale of interests

 

➢ Regulatory considerations: Assessing whether the structure may fall within broader regulatory frameworks, particularly where multiple investors or platforms are involved

 

➢ Operator and management risk: Reliance on third parties to manage the asset or platform

 

➢ Foreign ownership compliance: Ensuring that the property is located within areas where foreign ownership is permitted

 

In practice, many of the risks associated with fractional ownership arise not from the concept itself, but from insufficient or unclear documentation.

 

Conclusion

 

Fractional ownership in Dubai is best understood as a practical application of existing legal principles, rather than a distinct legal category. It offers a flexible way to access real estate by lowering the barrier to entry and spreading both risk and cost across multiple investors.

 

In a slightly downturned market, this model becomes particularly attractive. It allows investors to participate in real estate while limiting exposure, benefit from income-generating assets, and retain a degree of flexibility that may not be available with full ownership.

 

Ultimately, the success of any fractional ownership arrangement depends on clear structuring, strong governance, and well-drafted agreements. Where these elements are in place, it can serve as a balanced and commercially sensible approach to real estate investment in evolving market conditions. ■

Force Majeure in Real Estate Contracts: UAE Legal Position in a Period of Regional Instability

Introduction

 

Ongoing geopolitical tensions across the Middle East have brought renewed scrutiny to force majeure in UAE real estate transactions. While the UAE market remains resilient, indirect impacts, such as supply chain disruption, airspace restrictions, regulatory responses, and financing constraints, continue to affect performance across development, leasing, and investment structures.

 

Importantly, force majeure may be invoked under UAE law even in the absence of an express contractual provision. The concept arises as a matter of statute under the UAE Civil Code and operates independently of contractual drafting.

 

However, reliance on statutory force majeure is subject to a strict and narrow test, typically more onerous than contractual formulations.
This note outlines the legal framework and practical application of force majeure in the current environment, with reference to both contractual and statutory positions.

 

Legal Framework (UAE Law)

 

Under the UAE Civil Code:

 

– If performance becomes impossible, the obligation is extinguished;

– If impossibility is partial or temporary, performance may be suspended.

 

To qualify, the event must be:

 

– External to the parties;

– Unforeseeable at the time of contracting; and

– Render performance objectively impossible (not merely delayed or more expensive).

 

In the context of regional instability, the distinction between impossibility and hardship is critical. Disruption, delay, or cost escalation will rarely meet the statutory threshold absent a direct prevention of performance.

 

From a seller/landlord perspective, this high threshold offers protection against broad or opportunistic claims. From a buyer/tenant perspective, reliance on statute alone requires clear evidence of genuine impossibility.

 

Contractual Force Majeure

 

In practice, most UAE real estate contracts include bespoke force majeure provisions. These clauses typically take precedence, defining both the scope of qualifying events and the consequences of invocation.

 

Commonly included events in the current climate include:

 

– War, hostilities, or regional conflict;

– Government restrictions or regulatory action;

– Disruption to labour, logistics, or materials;

– Sanctions or financial restrictions.

 

The effectiveness of such clauses depends on drafting. Key variables include:

 

– Whether indirect effects (e.g. regional instability) are captured;

– The requirement for direct causation;

– The remedies available (suspension vs termination).

 

In practice, the contractual regime governs first, with statutory force majeure operating as a fallback where contracts are silent or unclear.

 

From a seller/landlord perspective, clauses are often drafted narrowly to preserve performance and limit termination exposure. Conversely, a buyer/tenant will seek broader wording to capture indirect disruption and secure flexibility.

 

Application in Real Estate Transactions

 

(a)  Development and Construction

 

Regional disruption may impact materials, labour, and approvals. These typically justify extensions of time, not termination, unless performance becomes impossible. Cost increases alone will not qualify.

 

A developer/seller will focus on preserving timelines through extensions, while a buyer will look to enforce longstop dates and delay remedies.

 

(b)  Leases

 

Tenants may seek rent relief due to operational disruption or reduced demand. However:

 

– Economic hardship is not force majeure;

– Relief depends on express lease provisions.

 

Absent clear drafting, rent obligations generally continue.

 

A landlord will rely on strict interpretation to enforce payment, while a tenant must anchor any relief in express contractual wording.

 

(c)  Sale and Purchase Agreements (SPAs)

 

Force majeure may arise where transfers or payments are delayed due to administrative or banking disruption. The typical outcome is deferral of completion, with termination linked to longstop dates.

 

A seller will resist termination and favour completion, while a buyer may seek exit rights where delay becomes prolonged.

 

Rights and Remedies

 

Where established, force majeure may result in:

 

– Suspension of obligations;
– Extension of time;
– Termination (in cases of permanent impossibility);
– Limited restitution.

 

Relief is conditional on strict compliance with:

 

– Notice provisions;
– Mitigation obligations;
– Evidence of causation.

 

From a seller/landlord perspective, remedies are structured to preserve contractual continuity. A buyer/tenant will focus on flexibility, including suspension or exit where justified.

 

Distinction from Exceptional Circumstances (Hardship)

 

Where performance is not impossible, but becomes excessively onerous, and Force Majeure is not available, parties may look to the doctrine of exceptional circumstances under the UAE Civil Code. Courts may rebalance obligations, though this remains discretionary and is applied conservatively.

 

Practical Considerations

 

– Causation is key: direct linkage between event and non-performance is essential.
– Foreseeability is shifting: ongoing tensions may weaken claims in new contracts.
– Drafting matters: tailored force majeure provisions are increasingly standard.
– Procedure is critical: failure to comply with notice or mitigation requirements may defeat a claim.

 

In practice, a seller/landlord will adopt a narrow, compliance-driven approach, while a buyer/tenant must build a robust evidentiary position to support relief.

 

Conclusion

 

Force majeure remains a high-threshold doctrine under UAE law. While regional instability creates real disruption, relief depends on demonstrating objective impossibility, not commercial inconvenience. Contractual provisions are central, but statutory force majeure remains available even where contracts are silent, subject to stricter requirements.

 

Where force majeure cannot be established, the doctrine of exceptional circumstances (hardship) offers a potential alternative, allowing courts to adjust obligations in cases of excessive burden. In the current environment, careful drafting, proactive contract management, and clear risk allocation remain essential.

Responsibilities and Code of Ethics for Real Estate Brokers in Dubai

Dubai’s property market continues to grow at record pace, attracting buyers from around the world. With this growth comes closer scrutiny of real estate brokers, who play a key role in keeping the market transparent, trustworthy, and compliant with regulations.

 

Why Broker Regulations Matter

Dubai strictly regulates real estate brokerage to protect investors and ensure fair dealings. Only trained, licensed, and registered brokers can broker real estate transactions. Regulatory bodies the Dubai Land Department (DLD) and the Real Estate Regulatory Agency (RERA) enforce clear rules, monitor behaviour, and penalise violations such as misleading ads or unlicensed activity.

 

What Brokers Must Do

Brokers in Dubai have legal duties that go far beyond connecting buyers and sellers. These include:

 

Holding proper licences and registrations: brokers must complete RERA training, pass exams, and carry valid broker IDs.

 

Keeping clear records: all transaction documents must be properly maintained and shared with clients when requested.

 

Being transparent: brokers must clearly disclose all relevant information, negotiation terms, and conditions.

 

Acting lawfully and in good faith: facilitation of any unlawful deal, or acts of fraud or deception, can lead to loss of commission and legal penalties.

 

Safeguarding client money: any funds or cheques entrusted to a broker must be protected and used only as agreed.

 

Earning commission properly: fees are due only when the broker successfully concludes the deal and fulfils agreed conditions.

 

Sharing liability when multiple brokers are involved: unless agreed otherwise, responsibility is joint.

 

Ethical Standards Brokers Must Follow

RERA’s Code of Ethics requires brokers to uphold professionalism at all times. Core expectations include:

 

Honesty, integrity, and respect: privacy, dignity, and transparency must guide all interactions.

 

Following all laws and regulations: no misleading advertising, false claims, or unauthorised activities.

 

Protecting documents: brokers must preserve all records linked to transactions.

 

Respecting DLD procedures: professional conduct is mandatory; personal connections may not be used to influence processes.

 

Practical Obligations in the Transaction Process

To safeguard buyers and sellers, brokers must comply with several operational rules:

 

Use RERA-standard forms: Form A (Seller), Form B (Buyer), and Form F/C (Sale).

 

Disclose commissions upfront: usually 1–5%, and always written in the contract.

 

Verify property ownership and documents: due diligence is mandatory.

 

Follow escrow (trust) account rules for off-plan projects: all payments must go into RERA-approved escrow accounts, not to brokers or to developers.

 

Advertise responsibly: Ads require RERA approval and must be accurate and non-misleading.

 

Meet AML/KYC requirements: brokers must verify client identity and report suspicious activity.

 

How Compliance Is Enforced

DLD and RERA actively monitor brokers through inspections, licence renewals, and mandatory training. Penalties for breaches are significant — including fines, warnings, and suspension of agents. Complaints from consumers can be filed directly with DLD, and unresolved matters can proceed to Dubai Courts.

 

Why This Matters to Consumers and Brokers

Dubai’s real estate success depends on transparency and trust. Licensed, ethical brokers have assisted to strengthen the market over decades; unprofessional practices damage the market overnight.

 

For brokers, professionalism is not optional. It is the foundation of credibility in a tightly regulated market. ■

Real Estate Dispute: Dubai Court of Cassation Clarifies Conditional Contracts and Manager Liability

The Dubai Court of Cassation (DCC) recently issued an important judgment in a real estate dispute, providing clarity on two key legal issues: the effect of suspensive conditions in conditional contracts and the personal liability of managers of limited liability companies (LLCs) in cases of fraud or misconduct.

 

Afridi & Angell acted for the buyer in this case.

 

Facts

 

– The buyer entered into a sale and purchase agreement (SPA) with a Dubai-based LLC (the seller) to purchase an off-plan property in the secondary market.

 

– The terms of the SPA required the buyer to pay nearly half the purchase price as a deposit, and the balance to be paid after the developer hands over the property.

 

– The contract contained additional terms – departing from the standard conditions of the Dubai Real Estate Regulatory Authority (RERA) – allowing the seller to encash the deposit cheques before completion. At the seller’s request, the cheques were addressed in the name of the manager of the seller entity (who was also the sole shareholder).

 

– The developer failed to hand over the property on time. While the buyer remained willing to proceed, the seller withdrew from the transaction and refused to return the deposit paid. Relying on the additional terms, the seller argued it was entitled to withdraw from the transaction and retain the deposit because the buyer was in breach of the contractual payment deadline.

 

– The buyer filed a claim against the seller and its manager, while the seller counterclaimed for damages.

 

Court Findings

 

Conditional Contracts

 

– The court found that completion of the sale was made conditional upon the developer’s handover of the project by a certain date. The court agreed with the buyer’s argument that this condition was a ‘suspensive condition’, and since it was not fulfilled within the contractual deadline, the seller was ordered to return the deposit to the buyer with interest.

 

 

– In appeal, the seller argued that in the context of an off-plan sale of property, delivery or handover of the project does not mean “actual” delivery of the property by the developer, but rather “constructive” delivery (i.e., transfer of title), which meant that the seller was ready to transfer the title to the buyer at all times. The DCC dismissed this ground and confirmed that pursuant to Articles 420 and 425 of the Civil Code, a conditional obligation is one that depends on the occurrence of a future or uncertain event, upon the happening of which, an obligation will either arise or cease. Where the obligation is subject to a suspending condition, it remains unenforceable until the relevant condition materialises or is fulfilled.

 

 

– On that basis, the DCC upheld the finding that the obligations of both parties (buyer to pay the balance and seller to transfer title) fell away as the suspending condition did not occur (i.e., handover of the project by the developer) without attributing a breach to either party. Accordingly, the lower court’s finding was upheld insofar as the deposit ought to be repaid to the buyer with interest. In this respect, the DCC opined that:

 

“A conditional obligation is one that depends upon a future and uncertain event, upon which the obligation either arises or is extinguished. If the condition is suspensive, it has the effect of suspending the enforceability of the obligation until the occurrence of that event upon which it depends.”

 

– The DCC held that the suspensive condition in the SPA has the effect of suspending “the enforceability of the plaintiffs’ obligation to pay the balance of the price until the occurrence of the event upon which it depends, namely the developer’s handover of the unit to the seller. The obligation to pay the balance of the price is deemed to exist during the suspension period but remains unenforceable, as it becomes operative only upon the occurrence of the condition.”

 

Liability of Manager

 

– The buyer sought to hold the seller’s manager personally liable on the basis of fraudulent conduct. The court upheld the buyer’s claim, finding that the manager had acted fraudulently by:

 

– depositing the buyer’s funds into his personal account,

 

– cancelling the seller entity’s trade license and concealing its liquidation during the court proceedings, and

 

– selling the property to a third party.

 

 

– The DCC confirmed that managers of an LLC are not personally liable for the company’s debts, except where fraudulent conduct, deceit, or bad faith is established. On the facts of this case, the DCC found that the manager had acted fraudulently and accordingly upheld the finding of personal liability.

 

Key Takeaways

 

– Suspensive conditions: This case illustrates the Dubai Courts’ approach to the interpretation of conditional contracts and obligations, ensuring that where a suspensive condition is not fulfilled, contracting parties are restored to their original positions. Where a contract is tied to a future event (e.g., project handover), and the event does not occur within the contractual deadline, the contract terminates automatically and any payments made must be returned.

 

– Manager liability: The judgment underscores the courts’ readiness to hold managers personally liable where fraud or misconduct is established. The DCC reaffirmed that, in exceptional cases, company managers can be held personally liable if they act dishonestly or misuse their position. ■

Buying Property with Cryptocurrency in Dubai

Dubai has emerged as a leading global destination for real estate investment and has increasingly positioned itself as a progressive, crypto-friendly jurisdiction. For prospective purchasers seeking to acquire property in Dubai using cryptocurrency, such as Bitcoin or Ethereum, it is essential to understand the regulatory framework, procedural requirements, and key considerations involved in such transactions.

 

Use of Cryptocurrency in Real Estate Transactions: Legal and Practical Considerations

 

Legality and Transaction Structure

 

Purchasing real estate in Dubai using cryptocurrency is legally permissible. However, transactions are not settled directly in virtual currencies. In accordance with applicable regulations, the cryptocurrency must first be converted into United Arab Emirates Dirhams (AED) through a licensed virtual asset service provider (VASP).

 

Transaction Process Overview

 

1 – Engage a Crypto-Compatible Real Estate Entity: Several real estate developers and brokerage firms in Dubai have entered into arrangements with regulated crypto platforms to facilitate property transactions funded via cryptocurrency. These entities assist buyers in navigating the process, including currency conversion and compliance procedures.

 

2 – Utilise a VARA-Licensed Exchange or Broker: In line with the UAE’s regulatory framework, the cryptocurrency must be converted into AED through a Virtual Assets Regulatory Authority (VARA)-licensed exchange or intermediary. This step includes full adherence to Know Your Customer (KYC) and Anti-Money Laundering (AML) obligations.

 

3 – Settlement in AED: Upon conversion, the purchase price is paid in AED.

 

4 – Completion of Legal Formalities: As with any real estate acquisition, standard due diligence and documentation are required. This includes verification of the title deed, execution of the sale and purchase agreement, and official registration of the transaction with the DLD.

 

Key Considerations

 

1 – Market Volatility: Cryptocurrency markets are inherently volatile. Accordingly, the timing of conversion from virtual assets to AED may significantly impact the final value available for the transaction. Prospective buyers should monitor market conditions closely.

 

2 – Regulatory Compliance: It is essential to engage only with entities that are licensed and regulated within the UAE. Transactions conducted through unregulated or informal channels may expose the buyer to legal and financial risks.

 

3 – Transaction Costs: Buyers should account for potential conversion fees, platform charges, and associated administrative costs when transferring funds from cryptocurrency to AED.

 

Conclusion

 

The use of cryptocurrency to fund real estate acquisitions in Dubai is gaining traction, particularly among international investors seeking efficient and borderless methods of payment. While this avenue offers flexibility and innovation, transactions must be conducted in full compliance with UAE regulatory requirements.

 

Engaging experienced professionals, specifically, legal advisors with expertise in UAE real estate laws, financial laws and crypto-enabled transactions is strongly advised to ensure lawful and secure execution. ■

Joint Venture Agreements in Real Estate Development Projects

Dubai’s development market is one of the most dynamic and rapidly growing real estate markets in the world, with consistent demand for residential, commercial, and mixed-use developments.

 

Developers frequently use Joint Venture (JV) agreements to collaborate on large-scale real estate and infrastructure projects, allowing them to share both the risks and rewards of large-scale developments.

 

In this inBrief, we discuss the types of JV agreements as well as their benefits, UAE specific considerations, and the key terms that should be considered to assist in reducing risks and disputes between JV parties.

 

Types of JV agreements

 

– Equity-based JV agreements: two or more partners create a new entity and share ownership, risks and profits based on their equity stakes.

 

– Special Purpose Vehicle (SPV): a common structure for JV agreements in real estate, where a new entity is created to handle a specific project, shielding the parent companies from some risks.

 

– Contractual JV agreements: parties collaborate on a project without sharing ownership of the project or forming a separate legal entity. Instead, the JV is governed purely by the terms of the agreement.

 

Benefits of JV agreements

 

JV’s offer several strategic advantages for developers and business partners such as:

 

– Access to capital and resources: developers can pool resources, capital and investors, allowing them to take on larger, more complex projects than they could on their own.

 

– Expertise and specialisation: developers can leverage each other’s expertise, for example, one partner might specialise in land acquisition, while another specialises in construction or design.

 

– Flexibility: JV’s allow developers to structure the agreement in a way that best suits the needs of the project, adjusting ownership percentages, management control, and profit sharing based on the contribution of each party.

 

– Risk sharing and liability: one of the main benefits of JV agreements in real estate is risk-sharing. The financial and operational risks associated with large projects are divided among the partners, reducing the exposure of each developer.

 

Key Considerations for Joint Venture (JV) Agreements in Dubai

 

When structuring a JV agreement in Dubai, developers should take into account the following important legal and regulatory aspects:

 

– Regulatory approvals: before commencing any development, developers must obtain regulatory approvals from the Dubai Land Department (DLD) and other relevant authorities. The JV agreement should include clauses that ensure compliance with local regulations, including but not limited to registration requirements, zoning laws, environmental standards, and such other requirements as may be applicable.

 

– Dispute resolution: in case of disputes, the JV agreement will typically contain provisions for dispute resolution, such as court, mediation or arbitration, especially when international parties are involved. The Dubai International Financial Centre (DIFC) and the Dubai International Arbitration Centre (DIAC) are common bodies for resolving such disputes when dealing with such complex matters.

 

The JV agreement should cover the following key elements:

 

– Project Scope and objectives: define the project’s location, size, design, budget, timeline, and expected returns.

 

– Ownership and control: a clear outline of the equity split, voting rights, decision-making authority, and dispute resolution procedures.

 

– Capital contribution and financing: specify each party’s capital contribution, identify debt financing sources, outline risk allocation, and processes for capital calls, distributions, and reinvestments.

 

– Profit sharing and exit strategy: clearly define how profit and loss sharing will be allocated, outline any preferred returns, and exit strategies such as selling, refinancing, or holding the project.

 

– Governance and reporting: establish the JV’s governance structure, assign key personnel, and set out meeting frequency, reporting requirements, and accounting methods.

 

– Contingencies and termination: outline the procedures for handling breaches of the agreement, including applicable penalties, termination conditions, and options for mutual buyout.

 

JV agreements are, therefore, a key tool for developers in Dubai, enabling them to pool resources and expertise for large-scale projects. These partnerships allow developers to share both the risks and rewards, making complex projects more manageable and financially viable. ■